The Sunwake Project

Design specification#

Sunwake SW-15 · SW-01 Rev 0 · August 2026

Companion to the design brief. This document records the engineering requirements behind the brief. Units are metric except for knots and nautical miles. Items marked [ENG] require calculation, CFD or FEA by the structural and hydrodynamic engineer of record before construction; the values shown are sizing assumptions, not approved figures. Any change to a bolded value or an [ENG] item requires a numbered revision. The design brief continues to govern intent.


SW-000 · General#

000.1 Principal particulars#

LOA / LWL canoe / LWL effective15.60 m / 15.00 m / 15.30 m
Beam overall / hull centres7.29 m / 5.00 m (s/L 0.33)
Demihull beam, waterline / deck1.404 m / 2.29 m
Draft, canoe body / to prop tips0.675 m / 0.95 m
Air draft, mast folded3.53 m
Bridgedeck clearance0.90 m (6.0 % LWL)
Displacement light / half / full11.80 t / 12.70 t / 13.58 t
Cp / Cm / Cb / Cwp0.592 / 0.735 / 0.435 / 0.731
LCB / LCF53.9 % / 58.1 % LWL
Wetted surface, canoe, both hulls48.4 m²
Propulsion2 × 60 kW peak, 25 kW continuous, DC input at the bus (see 200.1), short shafts
Battery / solar / generators128 kWh LFP at 352 V / 15 kWp / 2 × 20 kW variable-speed DC (HVO)
Structuretaped-seam plywood and epoxy, four developable strakes per side

000.2 Rules, standards and certification basis#

000.3 Weight and centre-of-gravity policy#

Bottom-up estimate at Rev 0 in the design brief §8. Margins: 6 % on lightship mass and +50 mm on VCG, held until as-built weighing; margin releases only against weighed data. Target LCG at half load 8.45 m abaft station 0 (56.3 % LWL); TCG on the centreline within ±25 mm. Every vendor substitution above 20 kg routes through the weight report, and the substitution log records the speed consequence at the moment the trade is made rather than at the weighing. The exchange rate is about 0.11 kt at solar noon per 500 kg. [ENG: maintain a live weight ledger; calc/sunwake/weights.py is the working copy.]


SW-100 · Hull and structure#

100.1 Materials#

100.2 Shell schedule (sizing basis, ISO 12215-5 Cat B) [ENG]#

ZonePlywoodOutsideInside
Hull bottoms15 mm600 g/m² biaxial400
Slam and forefoot zone, forward 30 %15 mm+ extra 600 biaxial, keel band with UHMWPE rub strip+ extra 400
Topsides12 mm400300
Hull decks12 mm450300
Watertight bulkheads15 mmtaped 3 × 450 biaxial, staggered 100/75/50 mm both faces
Partial bulkheads, frames, webs9 mm300 both faces
Wet deck (tunnel roof)15 mm on a plywood-web grid600 + 450450
Box beams15 mm webs and flanges450 × 2450
Deckhouse sides9 mm300300
Solar roof12 mm, or 2 × 6 mm over foam450300
Hull/deck and hull/wet-deck jointsdouble-lap 600 biaxial × 3, 100/75/50 mm staggersame

Design pressures, sizing basis: bottom slamming forward about 35 kN/m², wet-deck slam about 28 kN/m² over a 0.25 m² patch, topsides 12 kN/m². [ENG: confirm per ISO 12215-5; FEA the wet-deck panel. The largest open scantling choice is topsides at 12 mm against 9 mm plus stringers — about 94 m², about 135 kg, and a row shift in the plywood schedule.]

100.3 Internal structure#

100.4 Appendages#


SW-200 · Propulsion#

200.1 Motors and drives#

200.2 Shafting and propellers#

200.3 Steering#

Hydraulic two-station (helm plus two autopilot pumps, port and starboard independent), cylinders on each rudder arm, synchronising bar deleted in favour of electronically synced independent circuits with a divergence alarm. Full-flow bypass for the emergency tiller. Wing docking stations with electric jog levers commanding both drives and the rudders. No bow thruster — screws 5.0 m apart turn the boat in its own length. [ENG: failure-modes review of the steer-by-wire overlay.]


SW-300 · Electrical, high voltage#

300.1 Architecture#

Two mirrored propulsion islands, one per hull, cross-tied.

300.2 Sources and charging#

SourceHardwareNotes
Shore AC × 2 (50 A / 250 V each side)2 × 12 kW isolated on-board charger (PFC, 320–400 V out)fed through 2 × 7.5 kVA isolation transformers; 30 A adapters derate automatically
CCS1 DC inlet500 V / 200 A inlet and EVCC (ISO 15118 / DIN 70121), direct to bus through a dedicated contactor and prechargecapped near 120 kW at 128 kWh, 150 kW once the bank grows; interoperability test list in SW-800
Solar, 15 kWp8 strings to high-voltage MPPTs (250–450 V), four per hullstrings zoned so boom and mast shading sacrifices no more than 2 kWp
Generators2 × 20 kW variable-speed DC — see SW-500current-source onto the bus, droop-shared
AC out2 × 5 kVA inverter (230/120 V) for galley, outlets and the immersion elementpass-through on shore

The energy management supervisor (SW-320) enforces charge ceilings by temperature, solar-first dispatch, generator start rules (SOC below 25 % underway, below 15 % at anchor, or operator command) and the smart-load window: water heating, battery-bay heat and the optional watermaker follow solar surplus.

CCS is the least off-the-shelf item on the boat. Deleting it saves $15–25k but removes the ability to add half a charge during a lunch stop. Make the decision after quotations are received.

300.3 Low-voltage system#


SW-320 · Monitoring and control#


SW-400 · Ship systems#

400.1 Climate#

400.2 Fresh, black and grey#

400.3 Bilge and damage control#

Per hull: four compartments each with a 2,500 L/h automatic pump and float alarm, plus one 8,000 L/h 24 V crash pump with a strum box and camlock hose reachable to any compartment, plus a manual diaphragm pump in the cockpit locker. High-water alarms on the protected bus, repeated to telemetry. Collision-bulkhead voids foam-filled. Unsinkable-by-calculation is the target: reserve buoyancy in the sealed forepeak, after void and foam at least equal to the flooded hull mass. [ENG: verify, and run the downflooding review under ISO 12217-1.]

400.4 Fire#

400.5 Galley#

Induction, no propane aboard: two flush 3.7 kW zones managed to 5 kW combined by the energy management system, a 3 kW combination convection microwave, 130 L fridge and 75 L freezer drawers on 24 V compressors with keel-cooled condensers [ENG: consider sharing the heat-pump loop], and counters on a weight budget of 60 kg.


SW-500 · Generators and fuel#


SW-600 · Deck and equipment#


SW-700 · Interior and finishes#


SW-800 · Performance, noise and acceptance trials#

TestRequirement
Speed and power calibrationTwo-way GPS runs at 6/7/8/9/10/12/15 kt, calm, half load; record bus kW; deliverable is a calibrated range table loaded into the EMS
Silent range demonstration≥ 50 nm at 8 kt from 95 % to 15 % SOC, weather-corrected
Sprint15 kt sustained for 2 minutes at half load without derate; record bank draw and confirm the C-rate
Generator enduranceEach set 8 h at 16 kW; both 2 h at 32 kW; noise measured against the SW-500 limits
Underway noiseAt 8 kt: saloon ≤ 58 dB(A), cabins ≤ 55; at 12 kt saloon ≤ 65
CCS interoperabilitySuccessful sessions on at least two public 150 kW dispensers and one marine dispenser; graceful failure on handshake loss
Cold-charge lockoutDemonstrated at commissioning with a chilled tray sensor
Heat pumpCOP ≥ 3.2 at 8 °C seawater and 20 °C cabin
Steering and dockingLock to lock ≤ 12 s; box manoeuvre within 1.2 × LOA; wing-station authority demonstrated
StabilityISO 12217-1 Cat B compliance calculation plus inclining; stability booklet issued
Slam observationInstrumented head-sea run at about Hs 1.5 m; wet-deck accelerometer report [ENG]

SW-900 · Safety and compliance equipment#

Six-person valise liferaft in the cockpit locker · EPIRB and two PLBs · AIS-B+ with MOB integration · 24″ doppler radar with a thermal camera for the Maine fog package · LTE and satellite · two fixed DSC VHF plus two handhelds · lifejackets for six, four with auto-inflating harnesses, plus jacklines to the foredeck · MOB gear: Lifesling, throwline and the in-water-deployable transom ladders · foghorn with an automatic signal mode · offshore first-aid kit · lightning: air terminal on the mast, 70 mm² down-conductor to a submerged ground plate in each hull, surge protection at the high-voltage bus, at the low-voltage panels and at the masthead electronics (ABYC TE-4) · bonding and corrosion: full DC bond, isolation transformers so no galvanic isolator is needed, reference-electrode monitoring, anode plan per 100.4.


End SW-01 Rev 0. The open engineering items are compiled in open questions, which is also the statement-of-work attachment for the naval architect.