The Sunwake Project

Build timeline and cost#

Sunwake SW-15 · SW-BUILD Rev 1 · August 2026

This document follows Sunwake from the design contract through launch, showing what is built and paid for at each stage. It includes two estimates because they serve different purposes. Costing A covers materials and systems, with owner labour, shed and overhead excluded; it is useful for deciding whether the design is financially viable. Costing B reflects the chosen build plan: a full-time owner, one paid professional boatbuilder, a rented shed, and an owner-installed 352 V system with professional engineering, staged sign-offs and commissioning. This is the amount that must be financed. Costing A is roughly $0.57–0.97M. Costing B centres on $1.00M, with a range of $0.80–1.25M. Section 8 explains the difference. Figures are in mid-2026 USD; dimensions are metric, with knots and nautical miles retained. The nominal schedule is 26 months from design contract to launch.


1. What each costing assumes#

The two estimates include different costs:

Costing A — owner labour free, no overhead.

Costing B — the crewed scenario.


2. Effort#

The build scope, from Construction, scaled for Sunwake's panel areas:

PhaseHours (est.)
Hulls (2 × ~775)1,550
Join, beams, bridgedeck800
House, trunks, decks650
Fairing and paint950
Owner-side systems (LV, plumbing, mounts)450
Interior (incl. 2 hull cabins)700
Commissioning support, rig-out, margin400
Total≈ 5,500 (range 4,600–6,400)

A single owner working full time would need about 2.5–3 years. At 20 hours a week, the work would take 5–6 years, long enough for the finish on hull 1 to start ageing before hull 2 is faired. This is the main reason costing B includes a second pair of hands. The owner can do the work, but 950 hours of long-boarding creates a serious risk of delay or burnout.

Hulls can be built serially in a smaller bay and joined in rented space if 17 × 9.5 m is not available in one piece, but the join onwards needs the full envelope.


3. Costing A — materials and systems, owner labour free#

Line itemLowHigh
Design and engineering (lines, ISO 12215 book, HV one-line, kit files)$55k$95k
Structure and finish materials (ply, epoxy, glass, fairing, paint, glazing, deck hardware, interior materials)$85k$130k
CNC kit premium$10k$14k
Propulsion and HV electrical, professionally installed: 2 × 60 kW peak drives, 128 kWh at 352 V, 2 × 20 kW DC gensets, 15 kWp with MPPTs, OBCs / isolation / CCS / EMS, commissioning$250k$400k
Ship systems and equipment (heat pump, plumbing, tanks, nav and fog electronics, safety, ground tackle)$80k$135k
Tender, platform, roof-boom launch gear$15k$35k
Contingency (15–20 %)$74k$162k
Total≈ $0.57M≈ $0.97M

The professional high-voltage package is the largest single cost at 41–44 % of the boat. Compared with a low-voltage system, the 352 V architecture supports twin 20 kW DC generators, CCS charging, the ~15 kt sprint and the planned level of redundancy. See Generator selection and Electrical architecture and insurability.

Two levers sit inside the materials line. The Materials takeoff prices the bottom-up purchase plan — 250 sheets of plywood to order against a 310-sheet budget envelope, about 1,000 m² of glass including the tape inventory, 785 kg of epoxy, combined roughly $44–47k — and meranti instead of okoume saves a further $10–15k at about 15 % structure-weight cost, which the weight ledger will charge back at roughly 0.11 kt per 500 kg. The kit premium is separately examined in Cutting the kit, where owning the router instead of hiring one comes out close to a wash on cash and turns on schedule control.


4. Costing B — the crewed build, phase by phase#

Centre-case figures, each ±20 %. The running tally is cumulative spend, contingency included.

Phase 0 — Design, paperwork, mobilisation (months 1–4) · ≈ $116k · running $116k#

Phase 1 — Strongback, bulkheads, hull 1 (months 5–9) · ≈ $123k · running $239k#

Phase 2 — Hull 2 (months 9–11) · ≈ $41k · running $280k#

Phase 3 — Join, beams, bridgedeck, and the long-lead orders (months 11–14) · ≈ $141k · running $421k#

Phase 4 — House, trunks, decks (months 14–16) · ≈ $46k · running $467k#

Phase 5 — Fairing and paint (months 16–19) · ≈ $97k · running $564k#

Phase 6 — Systems and the owner-built 352 V install (months 19–23) · ≈ $292k · running $856k#

Phase 7 — Interior (months 21–24, overlapping) · ≈ $42k · running $898k#

Phase 8 — Rig-out, launch, commissioning, trials (months 24–26) · ≈ $102k · running ≈ $1.00M#


5. Where the money went#

Costing B, centre case, $k:

Category$k
Professional wages (~23 months)240
HV and propulsion incl. certified packs, oversight, commissioning280
Structure, finish and interior materials incl. CNC kit (15 % contingency)152
Ship systems and equipment (15 % contingency)107
Shed rent, fit-out and tooling97
Design and engineering (incl. trials support)64
Tender and launch gear (15 % contingency)29
Transport, crane, survey, insurance and fees32
Total≈ 1,000

Planning band for costing B: lean ≈ $0.80M (meranti, lower-cost vendor selections, $55/hr, 22 months) · centre ≈ $1.00M · high ≈ $1.25M (high HV quotes, 30 months).


6. Reconciling the two costings#

The gap between $0.57–0.97M and $1.00M comes from the costs included in each estimate.

Costing A prices the boat's contents: design, materials, kit, systems, the high-voltage package and a contingency on all of it. It deliberately values the owner's ~5,500 hours at zero and ignores everything that exists only because the boat is being built somewhere — rent, heat, tooling, the crane, the surveyor, the insurance premiums, the wide-load permit.

Costing B prices the project. Onto the same contents it adds about $240k of professional wages and about $110k of shed, overhead and launch logistics, and it moves the high-voltage install from the vendor's scope to the owner's — buying certified sealed packs and staged professional oversight instead of turnkey installation, which is close to a net wash at ≈ $280k against costing A's $250–400k line.

Without wages and overhead, costing B comes to about $630k, comfortably inside costing A's band and slightly above its midpoint. The estimates therefore agree on the cost of the boat itself. For financing purposes, however, the paid labour and shed cannot be omitted.

Use costing A to compare Sunwake with alternatives or to check whether individual items have drifted. Use costing B for financing, because it reflects the chosen build plan and its full cash requirement.


7. Alternatives if high-voltage quotes are too high#

The 352 V architecture accounts for the largest line in costing A. If quotations make it unaffordable, either fallback can use the same hull, lines and build sequence.

48 V fallback. A low-voltage version with two roughly 11–13 kW gensets, two 12–15 kW drives, an owner-assembled battery and an electrician's sign-off in place of a high-voltage integrator would cost roughly $0.39–0.71M on costing A's basis. It would give up CCS, the sprint and about a knot of generator passage speed, leaving a conventional displacement cruiser with less reserve speed for weather. Evaluate this option in Phase 0 if the high-voltage quotes and the underwriter's conditions make 352 V impractical.

96 V packaged ecosystem — an alternative architecture under study. The ePropulsion I-40 / G102 route is a single-vendor, dealer-supported CAN system: two I-40 inboards, twelve G102-100 packs for about 123 kWh, vendor solar controllers and roughly $85–110k of core hardware, compared with $250–400k for the professional 352 V package. Its clear product history and dealer support may make it easier to insure as an owner installation. The compromises are substantial: the vendor's prohibition on third-party chargers rules out the twin DC generator architecture, and there is no established 96 V DC genset market, so passage-making would require AC gensets feeding approved chargers. CCS would also go, and the sprint would fall to about 12.5 kt. In return, the system could save $150–250k and greatly simplify integration. The dealer RFQ questions needed to assess it are listed in Open questions.


8. Schedule risks#

The remaining risk is the owner's stamina. The 26-month schedule assumes a crewed build and consistent full-time participation from the owner for more than two years.


Cross-references: Design brief · Design specification · Construction · Materials takeoff · Generator selection · Electrical architecture and insurability · Cutting the kit · Naval architect engagement · Open questions